Wednesday, January 25, 2012

What a difference one year can make!


January 25, 2011
Demolition work progresses in preparation for construction on phase one of the 3-level underground parking garage. 
January 25, 2012
Phase one the of 3-level underground parking garage is
nearing completion!

Concrete columns will be poured today in preparation for construction of the new 25,000 square foot addition which is being built on top of the phase one portion of the underground.

When the new addition in completed later this summer, the library will temporarily move into the new space, utilizing the new underground parking, while the next phase of the project takes over. The final phase will see the complete renovation of all three floors of the original library building, and the construction of the second half of the underground parking garage.


Follow the project’s progress in photos at:
http://www.kpl.org/central/prg_photos.html

Read relevant project and library stories at:
http://www.kpl.org/central/prg_media.html

Join in the conversation at:
Facebook: www.facebook.com\kitchenerlibrary
Twitter: www.twitter.com\kitchlibrary